Our New Building

Our New Building

Construction of our new building at 5 Alliance Avenue Morisset has commenced.

Week 7 : 21st Oct 2019

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Week 6 : 14th Oct 2019

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Roof complete and wall sheeting started

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Week 5 : 7th Oct 2019

Roof Continues

 

 

 

 

 

 

 

Retaining Walls Under Construction

 

 

 

 

 

 

 

Week 4 : 30st Sep 2019

Concrete Panels Complete & Rood Started

 

 

 

 

 

 

 

Concrete Panels Installation

 

 

 

 

 

 

 

Steel Work Complete

 

 

 

 

 

 

 

Building steel work being erected

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Week 3 : 23rd Sep 2019

Retaining Walls Start

 

 

 

 

 

 

 

 

 

Retaining Wall & Steel Work Footings Poured

 

 

 

 

 

 

 

Week 2 : 16th Sep 2019

Work re-commences after 3 days of rain

 

 

 

 

 

 

 

Footings go in for steel work

 

 

 

 

 

 

 

Week 1 : 9th Sep 2019

Earthworks commences

Earthworks continue through the week

Site Ready For Retaining Wall Footings