Construction of our new building at 5 Alliance Avenue Morisset has commenced.
Week 7 : 21st Oct 2019
Week 6 : 14th Oct 2019
Roof complete and wall sheeting started
Week 5 : 7th Oct 2019
Week 4 : 30st Sep 2019
Week 3 : 23rd Sep 2019
Week 2 : 16th Sep 2019
Week 1 : 9th Sep 2019